The cost impact of a risk event occurring as a project proceeds through its life cycle tends to |
| A. | Slowly rise |
| B. | Slowly drop |
| C. | Drop sharply and then level out |
| D. | Rise sharply and then level out |
| Answer» A. Slowly rise | |