| Q. |
Which from the following represents the correct project cycle? |
| A. | Planning→Initiating→Executing→Closing |
| B. | Planning→Executing→Initiating→Closing |
| C. | Initiating→Planning→Executing→Closing |
| D. | Initiating→Executing→Planning→Closing |
| Answer» C. Initiating→Planning→Executing→Closing | |