Q.

Which from the following represents the correct project cycle?

A. Planning→Initiating→Executing→Closing
B. Planning→Executing→Initiating→Closing
C. Initiating→Planning→Executing→Closing
D. Initiating→Executing→Planning→Closing
Answer» C. Initiating→Planning→Executing→Closing