Q.

If a set of processes cannot be scheduled by rate monotonic scheduling algorithm, then

A. they can be scheduled by edf algorithm
B. they cannot be scheduled by edf algorithm
C. they cannot be scheduled by any other algorithm
D. none of the mentioned
Answer» C. they cannot be scheduled by any other algorithm
Explanation: none.