Q.

The time during which a machine remains waiting or vacant in sequencing problem is called time.

A. processing
B. waiting
C. free
D. idle
Answer» D. idle
1.2k
0
Do you find this helpful?
10

View all MCQs in

Operations Research

Discussion

No comments yet