McqMate
These multiple-choice questions (MCQs) are designed to enhance your knowledge and understanding in the following areas: Bachelor of Computer Applications (BCA) , Bachelor of Management Studies (BMS) .
1. |
________are entities whose value is determined from the solution of LPP |
A. | objective function |
B. | decision variable |
C. | constraints |
D. | opportunity cost |
Answer» A. objective function |
2. |
The region of feasible solution in LPP graphical method is called ____ |
A. | infeasible region |
B. | unbounded region |
C. | infinite region |
D. | feasible region |
Answer» D. feasible region |
3. |
The outgoing variable row in the simplex table is called ____ |
A. | outgoing row |
B. | key row |
C. | basic row |
D. | interchanging row |
Answer» C. basic row |
4. |
When the solution is degenerate in transportation problem, we add a _ |
A. | dummy |
B. | epsilon |
C. | penalty |
D. | regret |
Answer» B. epsilon |
5. |
______method is used in Assignment Problem |
A. | ncwr |
B. | lcm |
C. | vam |
D. | hungarian |
Answer» D. hungarian |
6. |
The longest path in the network diagram is called ____ |
A. | head path |
B. | sub path |
C. | critical path |
D. | sub critical path |
Answer» C. critical path |
7. |
IF the Minimax are ( 10,18,16) and Maximin are (8,10,7). The saddle point is ___ |
A. | 7 |
B. | 10 |
C. | 18 |
D. | 8 |
Answer» B. 10 |
8. |
Pick the wrong relationship: |
A. | interfering float = total float – free float |
B. | total float =free float + independent float |
C. | total float ≥ free float ≥ independent float |
D. | free float = total float – head event slack |
Answer» B. total float =free float + independent float |
9. |
The shortest time in the PERT is called ______time |
A. | expected |
B. | pessimitic |
C. | optimistic |
D. | most likely |
Answer» C. optimistic |
10. |
The total time required to complete all the jobs in a job sequence problem is known as ______ |
A. | processing order |
B. | idle time |
C. | processing time |
D. | elapsed time |
Answer» D. elapsed time |
11. |
Operations Research Models in which values of all variables and all possible outcomes are known with certainty are called models. |
A. | physical |
B. | symbolic |
C. | deterministic |
D. | probabilistic |
Answer» C. deterministic |
12. |
Operations Research Models in which some or all variables are random in nature are called models. |
A. | physical |
B. | symbolic |
C. | deterministic |
D. | probabilistic |
Answer» D. probabilistic |
13. |
and are techniques applied in project management. |
A. | cpm and pert |
B. | assignment & transportation |
C. | game theory |
D. | decision theory & inventory models |
Answer» A. cpm and pert |
14. |
are the entities whose values are to be determined from the solution of the LPP. |
A. | objective function |
B. | decision variables |
C. | constraints |
D. | opportunity cost |
Answer» B. decision variables |
15. |
specifies the objective or goal of solving the LPP. |
A. | objective function |
B. | decision variables |
C. | constraints |
D. | opportunity cost |
Answer» A. objective function |
16. |
_are the restrictions or limitations imposed on the LPP. |
A. | objective function |
B. | variables |
C. | constraints |
D. | profit |
Answer» C. constraints |
17. |
When it is not possible to find solution in LPP, it is called as solution |
A. | infeasible |
B. | unbounded |
C. | improper |
D. | unknown |
Answer» A. infeasible |
18. |
In case of a ‘ ’ constraint, the feasible region is a straight line. |
A. | less than or equal to |
B. | greater than or equal to |
C. | mixed |
D. | equal to |
Answer» D. equal to |
19. |
In linear programming, unbounded solution means solution. |
A. | infeasible |
B. | infinite |
C. | unique |
D. | degenerate |
Answer» B. infinite |
20. |
The incoming variable column in the simplex algorithm is called . |
A. | key column |
B. | incoming column |
C. | important column |
D. | variable column |
Answer» A. key column |
21. |
The intersection value of key column and key row is called |
A. | vital element |
B. | important element |
C. | basic element |
D. | key element |
Answer» D. key element |
22. |
The variable added to the LHS of a less than or equal to constraint to convert it into equality is called variable. |
A. | surplus |
B. | artificial |
C. | slack |
D. | additional |
Answer» C. slack |
23. |
A resource which is completely utilized is called in simplex |
A. | null resource |
B. | scarce resource |
C. | abundant resource |
D. | zero resource |
Answer» B. scarce resource |
24. |
In simplex, a minimization problem is optimal when all Delta J, i.e. Cj – Zj values are . |
A. | either zero or positive |
B. | either zero or negative |
C. | only positive |
D. | only negative |
Answer» A. either zero or positive |
25. |
To find initial feasible solution of a transportation problem the method which starts allocation from the lowest cost is called method |
A. | vogel’s approximat ion method |
B. | nwcr |
C. | lcm |
D. | modi |
Answer» C. lcm |
26. |
When the total of allocations of a transportation problem match with supply and demand values, the solution is called solution. |
A. | infeasible solution |
B. | feasible solution |
C. | optimum solution |
D. | degenerate solution |
Answer» B. feasible solution |
27. |
When the allocations of a transportation problem satisfy the rim condition (m + n – 1) the solution is called |
A. | infeasible solution |
B. | feasible solution |
C. | non degenerate solution |
D. | degenerate solution |
Answer» C. non degenerate solution |
28. |
Which of the following considers difference between two least costs for each row and column while finding initial basic feasible solution in transportation? |
A. | vam |
B. | nwcr |
C. | modi |
D. | lcm |
Answer» A. vam |
29. |
If the number of rows and columns in an assignment problem are not equal than it is called problem. |
A. | balanced |
B. | unbalanced |
C. | infeasible |
D. | unbounded |
Answer» B. unbalanced |
30. |
The method used for solving an assignment problem is called method. |
A. | vam |
B. | nwcr |
C. | modi |
D. | hungarian |
Answer» D. hungarian |
31. |
When a maximization assignment problem is converted in minimization problem, the resulting matrix is called matrix. |
A. | cost |
B. | regret |
C. | profit |
D. | dummy |
Answer» B. regret |
32. |
The longest path in the network diagram is called path |
A. | critical |
B. | sub-critical |
C. | best |
D. | worst |
Answer» A. critical |
33. |
Backward pass calculations are done to find occurrence times of events. |
A. | tentative |
B. | definite |
C. | latest |
D. | earliest |
Answer» C. latest |
34. |
The order in which machines are required for completing the jobs is called |
A. | machines order |
B. | job order |
C. | processing order |
D. | working order |
Answer» C. processing order |
35. |
The time during which a machine remains waiting or vacant in sequencing problem is called time. |
A. | processing |
B. | waiting |
C. | free |
D. | idle |
Answer» D. idle |
36. |
In linear programming represents mathematical equation of the limitations imposed by the problem. |
A. | objective function |
B. | decision variables |
C. | constraints |
D. | opportunity cost |
Answer» C. constraints |
37. |
The type of constraint which specifies maximum capacity of a resource is ‘or equal to’ constraint. |
A. | less than |
B. | greater than |
C. | not greater than |
D. | not less than |
Answer» A. less than |
38. |
The region of feasible solution in LPP graphical method is called region |
A. | infeasible |
B. | infinite |
C. | unbounded |
D. | feasible |
Answer» D. feasible |
39. |
When the constraints are a mix of ‘less than’ and ‘greater than’ it is a problem having . |
A. | multiple constraints |
B. | infinite constraints |
C. | infeasible constraints |
D. | mixed constraints |
Answer» D. mixed constraints |
40. |
The outgoing variable row in the simplex algorithm is called . |
A. | outgoing row |
B. | key row |
C. | interchanging row |
D. | basic row |
Answer» B. key row |
41. |
A resource which is partially utilized is called in simplex. |
A. | null resource |
B. | scarce resource |
C. | abundant resource |
D. | zero resource |
Answer» C. abundant resource |
42. |
The value of one extra unit of resource is called in simplex. |
A. | unit price |
B. | extra price |
C. | retail price |
D. | shadow price |
Answer» D. shadow price |
43. |
In simplex, a maximization problem is optimal when all Delta J, i.e. Cj – Zj values are . |
A. | either zero or positive |
B. | either zero or negative |
C. | only positive |
D. | only negative |
Answer» B. either zero or negative |
44. |
In a transportation problem, the method of penalties is called method. |
A. | vogel’s approximat ion method |
B. | nwcr |
C. | lcm |
D. | modi |
Answer» A. vogel’s approximat ion method |
45. |
When there is a degeneracy in the transportation problem, we add an imaginary allocation called in the solution. |
A. | dummy |
B. | penalty |
C. | regret |
D. | epsilon |
Answer» D. epsilon |
46. |
If M + N – 1 = Number of allocations in transportation, it means . (Where ‘M’ is number of rows and ‘N’ is number of columns) |
A. | there is no degeneracy |
B. | degeneracy exists |
C. | solution is optimum |
D. | problem is balanced |
Answer» A. there is no degeneracy |
47. |
An activity whose start or end cannot be delayed without affecting total project completion time is called activity. |
A. | dummy |
B. | non-critical |
C. | important |
D. | critical |
Answer» D. critical |
48. |
Floats for critical activities will be always be . |
A. | one |
B. | zero |
C. | highest |
D. | equal to duration |
Answer» B. zero |
49. |
The shortest possible completion time of an activity in PERT is called time. |
A. | optimistic |
B. | pessimistic |
C. | expected |
D. | most likely |
Answer» A. optimistic |
50. |
The total time required to complete all the jobs in a job sequencing problem is known as . |
A. | processing time |
B. | waiting time |
C. | elapsed time |
D. | idle time |
Answer» C. elapsed time |
Done Studing? Take A Test.
Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.