| Q. |
Which of the following is not project management goal? |
| A. | keeping overall costs within budget |
| B. | delivering the software to the customer at the agreed time |
| C. | maintaining a happy and well-functioning development team |
| D. | avoiding customer complaints |
| Answer» D. avoiding customer complaints | |
| Explanation: projects need to be managed because professional software engineering is always subject to organizational budget and schedule constraints. | |