McqMate
| Q. |
Which of the following is not a project factor that should be considered when planning the structure of software engineering teams? |
| A. | the difficulty of the problem to be solved |
| B. | high frustration caused by personal, business, or technological factors that causes friction among team members |
| C. | the degree of sociability required for the project |
| D. | the rigidity of the delivery date |
| Answer» C. the degree of sociability required for the project | |
| Explanation: development is irrelevant of social quotient. | |
View all MCQs in
Software Project Management (SPM)No comments yet