Q. |
A 66.6% risk is considered as |
A. | very low |
B. | low |
C. | moderate |
D. | high |
Answer» D. high | |
Explanation: the probability of the risk might be assessed as very low (<10%), low (10–25%), moderate (25–50%), high (50– |