Q.

Under normal conditions using an ordinary cement, the period of removal of the form work, is:

A. 7 days for beam soffits
B. 14 days for bottom slabs of spans 4.6 m and more
C. 21 days for bottom beams over 6 m spans
D. all the above
Answer» D. all the above