Q.
…………………….represents the start and end of an activity.
A.
event
B.
activity
C.
network
D.
slack
Answer» A. event
3.7k
0
Do you find this helpful?
43
View all MCQs in
Entrepreneurship Development (ED)
Discussion
No comments yet
Login to comment
Related MCQs
…………………….represents the start and end of an activity.
……………are activities that must be completed immediately prior to the start of another activity.
……is the unbroken chain of activities from start event to end event in the network diagram.
The sum of earliest start time and estimated time to perform the project is called……..
Which of the following provides services and advices to start up firms:
The sum of earliest start time and estimated time to perform the project is called……..
……………………….represents the activities and events of a project in a logical sequence.
………………………… is a network technique of scheduling and controlling the project where activity times cannot be precisely estimated.
Node represents…………………………
…………………..is the earliest time an activity can begin