

McqMate
Q. |
Maximum possible time to complete an activity is ……………………… |
A. | pessimistic time |
B. | optimistic time |
C. | most likely time |
D. | none of these |
Answer» A. pessimistic time |
View all MCQs in
Entrepreneurship Development (ED)No comments yet