Bottom-up testing |
A. | The low-level components of a system are integrated and tested before the higher-level components have been developed. |
B. | The testing process starts with modules at lower levels in the hierarchy and works up the hierarchy of modules until the final module is tested. |
C. | An event driven control system, where an event is broadcasted to each sub- system and any sub-system that can handle that event responds to it. |
D. | Control starts of the top of a sub routine hierarchy and through sub routine calls passes to lower levels. |
Answer» B. The testing process starts with modules at lower levels in the hierarchy and works up the hierarchy of modules until the final module is tested. |