Q.

The inspection of the project through the implementation phase is critical to ensure that quality standards are being met. The use of vendors is most often required to obtain critical materials, components, or sub-assemblies. To determine a vendor's capabilities to produce to the specifications, a "shop survey" or audit of the vendor may be required. e areas for the audit should include ______________.

A. facilities and shop space
B. experience and capability with similar work
C. quality assurance an control procedures
D. organization and quality of work in process
Answer» C. quality assurance an control procedures
542
0
Do you find this helpful?
1

Discussion

No comments yet

Related MCQs