Q.

A quality audit is a powerful tool in any quality improvement program. For a project that is starting a quality improvement program, the initial audit is used to ______________.

A. identify all the faculty work that has been completed
B. identify all the work that has been correctly accomplished
C. determine the single most urgent area for improvement
D. determine the quality baseline from which improvements will be made
Answer» D. determine the quality baseline from which improvements will be made