| Q. |
Which one of the following statements is NOT correct? |
| A. | LFT is calculated from the LFT of the head event. |
| B. | Slack can be calculated by adding EFT and LFT of any job. |
| C. | EFT is the sum of the EST and the time of duration for any event. |
| D. | The Total Project time is the shortest possible time required in completing the project. |
| Answer» B. Slack can be calculated by adding EFT and LFT of any job. | |