Which one of the following statements is NOT correct? |
A. | LFT is calculated from the LFT of the head event. |
B. | Slack can be calculated by adding EFT and LFT of any job. |
C. | EFT is the sum of the EST and the time of duration for any event. |
D. | The Total Project time is the shortest possible time required in completing the project. |
Answer» B. Slack can be calculated by adding EFT and LFT of any job. |