McqMate
Q. |
With reference to project management, identify which of the following statement is NOT correct? |
A. | Gantt chart is a principal tool used in scheduling and also in some methods of loading. |
B. | Routing is the first step in the production planning. |
C. | The cost of any activity is proportional to its time of completion. |
D. | The free float can be calculated by subtracting EFT from EST. |
Answer» D. The free float can be calculated by subtracting EFT from EST. |
View all MCQs in
Operations Management and Strategic ManagementNo comments yet