| Q. |
is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate. |
| A. | prime cost |
| B. | provisional sum |
| C. | capital cost |
| D. | building cost index |
| Answer» B. provisional sum | |
| Explanation: the work like installation of refrigerating machine; installation of lift, air conditioning, etc., for which full information | |