

McqMate
Q. |
is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate. |
A. | prime cost |
B. | provisional sum |
C. | capital cost |
D. | building cost index |
Answer» B. provisional sum | |
Explanation: the work like installation of refrigerating machine; installation of lift, air conditioning, etc., for which full information |
View all MCQs in
Estimation, Costing and Valuation EngineeringNo comments yet