McqMate
Q. |
The rates of materials used for government works are approved by |
A. | executive board |
B. | sdo |
C. | elective board |
D. | board of chief engineers |
Answer» D. board of chief engineers | |
Explanation: the board of chief engineers approves the rates of materials used for government works. however, every year, these are fixed by the superintendent engineer. |