Q.

A                    is developed using historical cost information that relates some software metric to the project cost.

A. algorithmic cost modelling
B. expert judgement
C. estimation by analogy
D. parkinson’s law
Answer» A. algorithmic cost modelling
Explanation: the model uses a basic regression formula with parameters that are derived from historical project data and current as well as future project characteristics.