Q. |
is required for preliminary studies of various aspects of a work or project. |
A. | supplementary estimate |
B. | plinth area estimate |
C. | revised estimate |
D. | abstract estimate |
Answer» D. abstract estimate | |
Explanation: to decide the financial position and policy for administrative sanction by the competent administrative authority. in case of |