McqMate
| Q. |
is required for preliminary studies of various aspects of a work or project. |
| A. | supplementary estimate |
| B. | plinth area estimate |
| C. | revised estimate |
| D. | abstract estimate |
| Answer» D. abstract estimate | |
| Explanation: to decide the financial position and policy for administrative sanction by the competent administrative authority. in case of | |
View all MCQs in
Estimation, Costing and Valuation EngineeringNo comments yet