………… is the earliest starting time plus ...
Q.
………… is the earliest starting time plus activity time.
A.
EST
B.
EFT
C.
LST
D.
LFT
Answer» B. EFT
2.5k
0
Do you find this helpful?
38
View all MCQs in
Principles of Management
Discussion
No comments yet
Login to comment
Related MCQs
……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity
Any activity which does not consume either any resource or time is called ………..activity.
An activity which must be completed before one or more other activities start is known as ……….activity.
An activity which must be completed before one or more other activities start is known as …………activity.
Even a small production activity like loading pigs of iron into boxcars can be scientifically planned and managed. This can result in tremendous saving of human energy as well as wastage of time and materials. Which of the following Principles if management emphasize on above situation?
The record of outcomes produced on a specific job function or activity during a specific time period is called
………. is the latest time by which an activity can be started without delaying the completion of the project.
……….is the latest time by which an activity can be finished without delaying the completion of the project.
………is the shortest possible time in which an activity can be delayed without delaying the project.
Time study involves analysing movements involved in performing an activity.