

McqMate
Q. |
……….is the latest time by which an activity can be finished without delaying the completion of the project. |
A. | EST |
B. | EFT |
C. | LST |
D. | LFT |
Answer» D. LFT |
View all MCQs in
Principles of ManagementNo comments yet