

McqMate
Q. |
……………is the duration by which an activity can be delayed without delaying the project |
A. | Slack |
B. | Total float |
C. | Free float |
D. | Independent float |
Answer» B. Total float |
View all MCQs in
Principles of ManagementNo comments yet