Q.

The phases of highway planning do not include the following?

A. assessment of road length requirement
B. preparation of master plan
C. showing the phasing of a plan in five year plan
D. financing
Answer» D. financing
Explanation: financing of the highway is done after the planning of the highway after getting approval from the government, before the assessment, preparation and dpr are prepared.