A drawback of bar chart is that |
| A. | All the activities are independent |
| B. | It is difficult to know whether activity is completed or not |
| C. | The sequence of activity is not clearly defined |
| D. | All of the above |
| Answer» C. The sequence of activity is not clearly defined | |