If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be |
A. | 1 + (0.9)010 |
B. | 1 - (0.9)°l0 |
C. | 1/(1-0.9°10) |
D. | 1/(1+ 0.9010) |
Answer» C. 1/(1-0.9°10) |