If the R.L's of canal bed level and high flood level of drainage are 212.0 m and 210.0 m respectively, then cross drainage work will be |
A. | aqueduct |
B. | superpassage |
C. | syphon |
D. | syphon aqueduct |
Answer» C. syphon |