The assumption in PERT is |
| A. | A project is always behind schedule |
| B. | Cost of project is always more than the estimated cost |
| C. | A project can be sub-divided into a set of predictable, independent activities |
| D. | Activities are complex in nature and time taken by them are indeterminate |
| E. | None of the above |
| Answer» C. A project can be sub-divided into a set of predictable, independent activities | |