

McqMate
Q. |
The assumption in PERT is |
A. | A project is always behind schedule |
B. | Cost of project is always more than the estimated cost |
C. | A project can be sub-divided into a set of predictable, independent activities |
D. | Activities are complex in nature and time taken by them are indeterminate |
E. | None of the above |
Answer» C. A project can be sub-divided into a set of predictable, independent activities |
View all MCQs in
Business ManagementNo comments yet