If D = duration, EF = earliest finish time, ES = earliest start time, LF = latest finish time, LS = latest start time, which relationship does not hold?

A. EF = D - ES
B. EF = D + ES
C. LF = LS + D
D. None of the above
E. Supply and demand conditions
Answer» A. EF = D - ES