In program evaluation review technique network each activity time assume a beta distribution because_________. |
| A. | it is a unimodal distribution that provides information regarding the uncertainty of time estimates of activities |
| B. | it has got finite non-negative error |
| C. | it need not be symmetrical about model value |
| D. | the project is progressing well |
| Answer» A. it is a unimodal distribution that provides information regarding the uncertainty of time estimates of activities | |