McqMate
| Q. |
The number of time estimates involved in Program Evaluation Review Technique problem is _______. |
| A. | 1 |
| B. | 2 |
| C. | 3 |
| D. | 4 |
| Answer» C. 3 | |
View all MCQs in
Computer Aided Optimisation TechniquesNo comments yet