In Program Evaluation Review Technique the maximum time that is required to perform the activity under extremely bad conditions is known as_____. |
| A. | normal time |
| B. | optimistic time |
| C. | most likely time |
| D. | pessimistic time |
| Answer» D. pessimistic time | |