In Program Evaluation Review Technique for an activity, the optimistic time 2, the pessimistic time is 12 and most-likely time is 4. What is the expected time? |
| A. | zero |
| B. | 1 |
| C. | 5 |
| D. | 6 |
| Answer» C. 5 | |