McqMate
| Q. |
Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks? |
| A. | software macroscopic schedule |
| B. | software project scheduling |
| C. | software detailed schedule |
| D. | none of the mentioned |
| Answer» B. software project scheduling | |