Which estimation technique can be used if interfaces to software synthesis tools and hardware synthesis tools exist? |
| A. | performance value |
| B. | estimated cost |
| C. | estimated cost and performance value |
| D. | accurate cost and performance value |
| Answer» D. accurate cost and performance value | |
| Explanation: the accurate cost and performance value is possible if interfaces to software synthesis tools and hardware synthesis tools exist. | |