Q.

PERT.

A. both (i) and (iii) above
B. both (i) and (iv) above
C. both (ii) and (iv) above
D. both (ii) and (iii) above
Answer» B. both (i) and (iv) above
Explanation: two tools for computing critical path and project completion times from activity networks are cpm &pert