Q.

Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks?

A. software macroscopic schedule
B. software project scheduling
C. software detailed schedule
D. none of the mentioned
Answer» B. software project scheduling
Explanation: none.
1.8k
0
Do you find this helpful?
3

Discussion

No comments yet