Q. |
What is the recommended distribution of effort for a project? |
A. | 40-20-40 |
B. | 50-20-30 |
C. | 30-40-30 |
D. | 50-30-20 |
Answer» A. 40-20-40 | |
Explanation: a recommended distribution of effort across the software process is 40% (analysis and design), 20% (coding), and 40% (testing). |