It ………. at which an activity can start....
Q.
It ………. at which an activity can start.
A.
est
B.
eft
C.
lst
D.
lft
Answer» A. est
1.6k
0
Do you find this helpful?
11
View all MCQs in
Management Science
Discussion
No comments yet
Login to comment
Related MCQs
……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity
An activity which must be completed before one or more other activities start is known as …………activity.
………. is the latest time by which an activity can be started without delaying the completion of the project.
……….is the latest time by which an activity can be finished without delaying the completion of the project.
……………is the duration by which an activity can be delayed without delaying the project
………… is the duration by which an activity can be delayed without delaying the project.
………is the shortest possible time in which an activity can be delayed without delaying the project.
..................... is the duration by which an activity can be delayed without delaying the completion of the project.
............................ is the latest time by which an activity can be finished without delaying the completion of the project.
.......................... is the duration by which an activity can be delayed without delaying the project.