..................... is the duration by which an activity can be delayed without delaying the completion of the project. |
| A. | Earliest Start Time |
| B. | Earliest Finish Time |
| C. | Latest Start Time |
| D. | Latest Finish Time |
| Answer» C. Latest Start Time | |