Q.
………… is the earliest starting time plus activity time.
A.
est
B.
eft
C.
lst
D.
lft
Answer» B. eft
2.6k
0
Do you find this helpful?
38
View all MCQs in
Management Science
Discussion
No comments yet
Login to comment
Related MCQs
……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity
An activity which must be completed before one or more other activities start is known as …………activity.
………. is the latest time by which an activity can be started without delaying the completion of the project.
……….is the latest time by which an activity can be finished without delaying the completion of the project.
………is the shortest possible time in which an activity can be delayed without delaying the project.
An activity which does not consume either resource or time is called .............................
............................ is the latest time by which an activity can be finished without delaying the completion of the project.
An event which represents the beginning of more than one activity is known as ………..event.
It ………. at which an activity can start.
……………is the duration by which an activity can be delayed without delaying the project