Q.

Material price variance is the difference between standard and actual prices of materials used multiplied by………………..

A. Actual quantity of materials used
B. Budgeted quantity of materials used
C. Standard quantity of materials used
D. Either a or b
Answer» A. Actual quantity of materials used