Total Material cost variance = |
A. | Standard cost of materials-actual cost of materials |
B. | Budgeted cost of materials- actual cost of materials |
C. | Standard cost of materials-budgeted cost of materials |
D. | Actual cost of materials- budgeted cost of materials |
Answer» A. Standard cost of materials-actual cost of materials |