| Q. |
The ratio of work done by (x + 2) men in (x – 2) days to that (x – 1) men in (x + 1) days is 4 : 5, the value of x is |
| A. | + 4 |
| B. | 6 |
| C. | 4 |
| D. | 8 |
| Answer» C. 4 | |