In a PERT network, slack time is _____. |
A. | The end point that represents the completion of a major activity |
B. | The time or resources required to progress from one event to another |
C. | The amount of time an individual activity can be delayed without delaying the whole Project |
D. | The longest or most time-consuming sequence of events and activities |
Answer» C. The amount of time an individual activity can be delayed without delaying the whole Project |