Free float is mainly used to |
| A. | Identify the activities which can be delayed without affecting the total float of preceding activity |
| B. | Identify the activities, which can be delayed without affecting the total float of succeeding activity |
| C. | Establish priorities |
| D. | Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities |
| Answer» B. Identify the activities, which can be delayed without affecting the total float of succeeding activity | |