Total float for any activity is defined as the difference between |
| A. | Its latest finish time and earliest start time for its successor activity |
| B. | Its latest start time and earliest start time |
| C. | Its latest start time and earliest finish time |
| D. | Its earliest finish time and earliest start time for its successoractivity |
| Answer» B. Its latest start time and earliest start time | |