133
77.1k

160+ Construction Management Solved MCQs

These multiple-choice questions (MCQs) are designed to enhance your knowledge and understanding in the following areas: Civil Engineering .

1.

In time-cost optimization of a project, crashing is done.

A. On all the activities
B. On all the activities lying on the critical path
C. Only on activities lying on the original critical path and having flatter costslopes
D. On original critical activities and those that become critical at any stage of crashing inthe order of ascending cost slope
Answer» D. On original critical activities and those that become critical at any stage of crashing inthe order of ascending cost slope
2.

Which of the following does not represent an activity?

A. Site located
B. Foundation is being dug
C. The office area is being cleaned
D. The invitations are being sent
Answer» A. Site located
3.

In resources levelling

A. Total duration of project isreduced
B. Total duration of project isincreased
C. Uniform demand of resources is achieved
D. Cost of project is controlled
Answer» C. Uniform demand of resources is achieved
4.

Sensitivity analysis is a study of

A. Comparison of profit and loss
B. Comparison of assets and liabilities
C. Change in output due to change in input
D. Economics of cost and benefits of the project
Answer» C. Change in output due to change in input
5.

Preliminary project report for a road project must contain

A. The detailed estimated cost based on detailed design
B. The several alternatives of the project that have been considered
C. The soil survey, traffic survey, concept design and approximate cost
D. The contract documents for inviting tenders
Answer» C. The soil survey, traffic survey, concept design and approximate cost
6.

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam
B. Good common earth
C. Well blasted rock
D. Wet sticky clay
Answer» A. Moist loam
7.

If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be

A. Equal to X
B. More than X
C. Less than X
D. Any of the above
Answer» C. Less than X
8.

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve
B. Poisson's distribution curve
C. Beta distribution curve
D. None of the above
Answer» C. Beta distribution curve
9.

Free float is mainly used to

A. Identify the activities which can be delayed without affecting the total float of preceding activity
B. Identify the activities, which can be delayed without affecting the total float of succeeding activity
C. Establish priorities
D. Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Answer» B. Identify the activities, which can be delayed without affecting the total float of succeeding activity
10.

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

A. Concrete
B. Loose sand
C. Asphalt
D. Firm earth
Answer» B. Loose sand
11.

Which of the following earth moving machines has the shortest cycle time?

A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel
Answer» D. Dipper shovel
12.

Updating may result in

A. Change of critical path
B. Decrease of project completion time
C. Increase of project completion time
D. All of the above
Answer» D. All of the above
13.

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

A. Total float
B. Free float
C. Interfering float
D. Independent float
Answer» D. Independent float
14.

During the construction period, price variation clause in contracts caters to

A. Increase in rates of only importantmaterials
B. Variation in cost in materials element, labour element and petrol-oil-lubricantelement
C. Variation in total cost of the project on an ad hocbasis
D. Rate of inflation
Answer» B. Variation in cost in materials element, labour element and petrol-oil-lubricantelement
15.

Critical path method

A. Is an improvement upon bar chart method
B. Provides a realistic approach to daily problems
C. Avoids delays which are very common in bar charts
D. All the above
Answer» D. All the above
16.

At a work site, statistical quality control of concretemeans

A. Measurement of risks to eliminate failures
B. Applying the theory' of probability to sample testing or inspection
C. Reduction in wastage of inspection costs
D. Reduction in costs for the removal of defects
Answer» B. Applying the theory' of probability to sample testing or inspection
17.

For the network shown in the given figure, the expected time for the activity

A. 1-2 is 4
B. 2-3 is 7
C. 3-4 is 8
D. All the above
Answer» D. All the above
18.

A critical ratio scheduling

A. Determines the status of each activity
B. Adjusts automatically changes in activity progress
C. Is a dynamic system
D. None of these
Answer» D. None of these
19.

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

A. 8 days
B. 9 days
C. 10 days
D. 15 days
Answer» B. 9 days
20.

Pick up the correct statement from the following:

A. Optimistic time estimate refers to activities
B. Pessimistic time estimate refers toactivities
C. Most likely time estimate refers to activities
D. All the above
Answer» D. All the above
21.

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer» C. Least cost slope
22.

A golden rule for the procurement of construction stones, suggests

A. 100% at the site
B. 67% at the site and 33% under procurement
C. 50% at the site and 50% under procurement
D. 33% at the site and 67% under procurement
Answer» B. 67% at the site and 33% under procurement
23.

The time with which direct cost does not reduce with the increase in time is known as

A. Crash time
B. Normal time
C. Optimistic time
D. Standard time
Answer» B. Normal time
24.

Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest starttime
B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
D. All the above
Answer» D. All the above
25.

Interfering float is the difference between

A. Total float and free float
B. Total float and independentfloat
C. Free float and independentfloat
D. None of the above
Answer» A. Total float and free float
26.

While filling the tender for any work, the contractor considers

A. Site survey
B. Availability of construction materials
C. Availability of labour
D. All the above
Answer» D. All the above
27.

An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

A. Rs. 8,43,750
B. Rs. 8,75,000
C. Rs. 10,50,000
D. Rs. 11,56,250
Answer» A. Rs. 8,43,750
28.

Pick up the incorrect statement from the following:

A. The various functions under each activity, are shown by one bar on Bar Charts
B. Bar chart establishes the interdependency of one event on another
C. Only approximate percentage of the completed work isreported
D. None of these
Answer» B. Bar chart establishes the interdependency of one event on another
29.

A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is

A. 10000 kg
B. 12500 kg
C. 22500 kg
D. 5000 kg
Answer» B. 12500 kg
30.

If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be

A. 2.3% and 84.1%
B. 97.7% and 84.1%
C. 97.7 % and 15.9%
D. 15.9% and 97.7%
Answer» A. 2.3% and 84.1%
31.

Power stations are generally treated as

A. Light construction
B. Heavy construction
C. Industrial construction
D. Electrical construction
Answer» C. Industrial construction
32.

For a given size of bucket, the ideal output of a dragline will be least in

A. Moist loam
B. Sand and gravel
C. Good common earth
D. Wet sticky clay
Answer» D. Wet sticky clay
33.

Bar charts are suitable for

A. Minor works
B. Major works
C. Large projects
D. All the Above
Answer» A. Minor works
34.

The time corresponding to minimum total project cost is

A. Crash time
B. Normal time
C. Optimistic time
D. Between normal time and crash time
Answer» D. Between normal time and crash time
35.

Construction team means

A. An engineer
B. An architect
C. An owner
D. All the above
Answer» D. All the above
36.

Select the incorrect statement.

A. Start float and finish float are always equal.
B. Total float can be either start float or finish float.
C. Start float and finish float need not be equal.
D. Start float and finish float are the differences between activity times and notevent times.
Answer» C. Start float and finish float need not be equal.
37.

The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

A. Event
B. Free float
C. Dummy
D. Constraint
Answer» C. Dummy
38.

PERT technique of network analysis is mainly useful for

A. Small projects
B. Large and complex projects
C. Research and development projects
D. Deterministic activities
Answer» C. Research and development projects
39.

Pick up the correct statement from the following:

A. The float may be positive, zero or negative
B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
D. All the above
Answer» D. All the above
40.

The independent float affects only

A. Preceding activities
B. Succeeding activities
C. The particular activity involved
D. None of the above
Answer» C. The particular activity involved
41.

Site order book is used for recording

A. Instructions by the executive engineers
B. Construction measurements
C. Issue of store equipments
D. Names of the casual labour
Answer» A. Instructions by the executive engineers
42.

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration
B. Total float
C. Free float
D. Interfering float
Answer» C. Free float
43.

The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements

A. (i), (ii) and (iv) are correct
B. (ii), (iii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i), (ii) and (iii) are correct
Answer» D. (i), (ii) and (iii) are correct
44.

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg
B. 300 kg
C. 900 kg
D. 1000 kg
Answer» C. 900 kg
45.

Works costing less than Rs. 20,000 are treated as

A. Any project
B. Major projects
C. Minor projects
D. All the above
Answer» C. Minor projects
46.

A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be

A. Rs. 1740
B. Rs. 3480
C. Rs. 5220
D. Rs. 6960
Answer» B. Rs. 3480
47.

Railway projects are treated as

A. Light construction
B. Heavy construction
C. Industrial construction
D. None of these
Answer» B. Heavy construction
48.

Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float. Of these statements

A. 1 and 4 are correct
B. 2 and 3 are correct
C. 1 and 4 are correct
D. 1 and 2 are correct
Answer» B. 2 and 3 are correct
49.

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
C. The difference between total float and free float, is called interfering float
D. All the above
Answer» D. All the above
50.

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800
B. Rs. 7,600
C. Rs. 6,400
D. Rs. 5,000
Answer» C. Rs. 6,400

Done Studing? Take A Test.

Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.