Which method is adopted to develop an approximate or conceptual estimate for perimeter works for buildings from the following? |
A. | Base unit method |
B. | Cost per function method |
C. | Cost per square metre method |
D. | Cost per linear metre method |
Answer» D. Cost per linear metre method |