| Q. |
Which method is adopted to develop an approximate or conceptual estimate for perimeter works for buildings from the following? |
| A. | Base unit method |
| B. | Cost per function method |
| C. | Cost per square metre method |
| D. | Cost per linear metre method |
| Answer» D. Cost per linear metre method | |