Pick up the correct reason for making conceptual (or preliminary) estimate from the following: |
| A. | To have a check on a definitive cost estimate |
| B. | To check quotations from contractors and/or sub-contractors |
| C. | To compute target estimate for the owner while drawing and specifications are in initial stage |
| D. | All of these |
| Answer» D. All of these | |