Pick up the correct reason for making conceptual (or preliminary) estimate from the following: |
A. | To have a check on a definitive cost estimate |
B. | To check quotations from contractors and/or sub-contractors |
C. | To compute target estimate for the owner while drawing and specifications are in initial stage |
D. | All of these |
Answer» D. All of these |