Q.

Pick up the correct reason for making conceptual (or preliminary) estimate from the following:

A. To have a check on a definitive cost estimate
B. To check quotations from contractors and/or sub-contractors
C. To compute target estimate for the owner while drawing and specifications are in initial stage
D. All of these
Answer» D. All of these